Scope:
Relocation of the raw water pipeline section currently located within the Gaoxing Company premises to land under the jurisdiction of the Taipei Water Department.
1.Installation of 6 meters of ∮3200mm STP straight pipe (including fittings).
2.Installation of 26 meters of ∮2600mm STP straight pipe (including fittings).
3.Installation of 62.4 meters of ∮2600mm DIP straight pipe (including fittings).
4.Installation of 1 set of ∮200mm resilient seated gate valve.
5.Installation of one ∮200mm combination air valve.
6.Decommissioning of the existing raw water culvert in place, totaling approximately 91 meters in length.
Benefits:
Replacement of aging raw water supply pipeline sections to reduce leakage and improve water supply quality.
Project Cost: USD 2.2 million
Construction Period: September 2023 to July 2024